Overview

Plan replenishment by setting the order deadline from SKU-level stock cover and confirmed receipt lead time, then sizing the order from projected stock at arrival. Use sell-through history to challenge the demand assumption—not as a substitute for daily sales. Before release, reconcile the quantity with confirmed pack-ordering rules, MOQ and the receiving window. The result should be a dated decision for each SKU: order now, schedule release, or hold with a specific condition to resolve.

Diagram: How to Plan Replenishment from Confirmed Lead Time and Sell-Through Data

What records and confirmed figures does a reorder review need?

A reorder review needs matched sales and inventory records, a confirmed lead time to usable receipt, and the commercial conditions for the exact configuration and destination.

Keep the SKU, variant, packaging revision, destination and inventory location together. Calculate demand separately where channels have dedicated stock; where channels share one pool, reconcile their demand against that shared stock without counting it twice. Channel-level supply reviews and early inclusion of MOQ and lead time are practical recommendations also made by Plan + Pivot Collective.

For lead time, request a dated confirmation identifying the start event—such as accepted order, payment or artwork approval—and the endpoint. Factory dispatch is not usable warehouse receipt. Include the applicable production, transport and receiving stages without counting an included stage twice. Record calendar or business days, order cutoffs, availability and any documents needed before release.

How do sell-through and days of cover inform different decisions?

Sell-through reviews the previous buy, while days of cover estimates how long current stock will last at the selected sales rate.

For this review, sell-through rate = units sold ÷ units received during the stated period × 100%. Days of cover = current usable stock ÷ average daily unit sales. These definitions follow eBrands inventory guidance. Keep the receipt-period definition consistent: sales from opening stock can distort the ratio, so show opening stock alongside it rather than treating the percentage as an isolated verdict.

Average daily sales = units sold ÷ days in the selected observation period. Use a period that represents the demand you are replenishing. If the SKU was unavailable, dividing sales by every calendar day can understate demand; flag those days and document any adjustment rather than silently treating unavailable days as zero demand.

A high sell-through percentage does not establish an order quantity on its own. Use the underlying unit-sales rate, check whether it remains relevant, and project demand to arrival. If average daily sales are zero, do not divide by zero or use an automatic cover-based reorder; review whether replenishment is justified at all.

How do you calculate the reorder trigger and order window?

Set the reorder trigger at the point where remaining cover equals confirmed replenishment lead time plus the buyer’s justified buffer.

For steady sales with no intervening receipts, let D be the review date, C be current days of cover, L be confirmed lead time and B be the buyer-approved buffer in days. The trigger date is D + C − L − B. The latest acceptable usable-receipt date is D + C − B. Round fractional deadlines toward the earlier workable ordering date.

The trigger is an order-release deadline, not an arrival date. If it has already passed, record the overdue deadline and act today; do not move it forward to make the worksheet look current. Schedule the next review before the deadline, allowing time for internal approval and any supplier cutoff.

Calculate the placement window by working backward from the required receiving window using the confirmed lead time, then intersect it with supplier ordering cutoffs. If lead time starts only after payment or specification approval, those conditions must be completed by the calculated start date.

Use dated inventory balances when outstanding receipts or uneven demand make the simple formula unsuitable. A receipt arriving after a projected shortage does not cover the earlier gap. An average historical lead time can also leave a gap when the actual receipt takes longer; it is not a substitute for current confirmation. The variability risk is discussed in eBrands inventory guidance. Neither confirmation nor a buffer guarantees an arrival.

Choose B from your own receipt variability and shortage exposure, not from a universal stock-cover rule. If you deliberately use no buffer, record that decision.

How do you turn the demand calculation into a placeable quantity?

Calculate the stock needed after receipt, subtract projected usable stock at that receipt, and only then apply MOQ and confirmed ordering restrictions.

Let r be the buyer-selected daily demand rate, H be the buyer-approved days-of-cover target immediately after receipt, and A be projected usable stock immediately before that receipt. Raw order quantity = max(0, r × H − A). Include relevant existing receipts in A and account for allocations once. H must come from the buyer’s own purchasing policy and records; if it already includes buffer stock, do not add the buffer again.

For an integer-unit order with no confirmed order multiple, the minimum candidate is max(raw quantity rounded up to a whole unit, MOQ). If a full-pack multiple p is explicitly required, the candidate is p × ceiling[max(raw quantity, MOQ) ÷ p]. MOQ is a minimum, not a multiple.

For optional full-carton purchasing, calculate carton-rounded quantity separately as carton quantity × ceiling[candidate quantity ÷ carton quantity]. Compare the added units and resulting cover before accepting them. Do not turn a packing detail into a purchasing restriction.

When should the buyer hold, revise or escalate the reorder?

Hold or revise the order whenever the proposed quantity or timing cannot be supported by confirmed conditions and the buyer’s approved inventory limits.

If raw demand is below MOQ, show the additional units attributable to the minimum and their effect on cover. Approve that increase explicitly or decline the reorder. Reaching MOQ is not evidence that the extra stock is needed.

When pack rounding exceeds the approved cover target, record either acceptance of the extra units or rejection of the larger order. Seek a different pack arrangement only as a request—not as an assumed supplier service.

If the placement window has closed, do not describe the original arrival as achievable. Escalate for a newly confirmed schedule, assess the projected shortage, and revise or defer the order. If current lead time is unconfirmed, hold the release decision rather than presenting an assumed figure as confirmed.

Close the review with the approver’s name and date, the released quantity, accepted order conditions and confirmation reference. Update it when timing changes, then reconcile actual usable receipt against the plan. A dated record supports traceability; it does not itself prevent a stockout or reveal an undisclosed supplier change.